Financial year Period Defect category Overall % of tests Overall % of defects Dangerous defects % of tests Dangerous defects % of defects Major defects % of tests Major defects % of defects
2023 to 2024 Total Identification of the vehicle 1.03% 3.99% Not set Not set 1.03% 5.13%
2023 to 2024 Total Motorcycle audible warning (Horn) 0.07% 0.28% Not set Not set 0.07% 0.36%
2023 to 2024 Total Motorcycle brakes 3.49% 18.47% 1.32% 25.32% 2.55% 16.52%
2023 to 2024 Total Motorcycle lamps and reflectors 8.02% 40.97% 1.06% 18.76% 7.30% 47.29%
2023 to 2024 Total Motorcycle steering 1.33% 5.80% 0.36% 6.65% 1.03% 5.55%
2023 to 2024 Total Motorcycle structure and attachments 2.29% 11.24% 0.53% 10.06% 1.90% 11.58%
2023 to 2024 Total Motorcycle suspension 2.03% 9.51% 0.18% 3.37% 1.89% 11.26%
2023 to 2024 Total Motorcycle tyres 2.05% 8.98% 1.77% 34.73% 0.31% 1.65%
2023 to 2024 Total Motorcycle wheels 0.18% 0.76% 0.06% 1.11% 0.12% 0.66%
2023 to 2024 Total Overall Initial Failure Rate 14.62% Not set 4.60% Not set 10.03% Not set
2023 to 2024 Total Average defects per Initial Test Failure Not set 1.78 Not set 0.39 Not set 1.39
2023 to 2024 Quarter 4: January to March Identification of the vehicle 1.02% 3.80% Not set Not set 1.02% 4.97%
2023 to 2024 Quarter 4: January to March Motorcycle audible warning (Horn) 0.07% 0.26% Not set Not set 0.07% 0.34%
2023 to 2024 Quarter 4: January to March Motorcycle brakes 3.87% 19.76% 1.58% 27.65% 2.75% 17.34%
2023 to 2024 Quarter 4: January to March Motorcycle lamps and reflectors 8.19% 39.85% 1.14% 18.51% 7.43% 46.39%
2023 to 2024 Quarter 4: January to March Motorcycle steering 1.49% 6.23% 0.41% 6.89% 1.15% 6.02%
2023 to 2024 Quarter 4: January to March Motorcycle structure and attachments 2.39% 11.46% 0.57% 9.82% 1.97% 11.96%
2023 to 2024 Quarter 4: January to March Motorcycle suspension 1.95% 8.89% 0.20% 3.37% 1.79% 10.58%
2023 to 2024 Quarter 4: January to March Motorcycle tyres 2.13% 8.99% 1.83% 32.72% 0.33% 1.72%
2023 to 2024 Quarter 4: January to March Motorcycle wheels 0.19% 0.76% 0.06% 1.03% 0.13% 0.68%
2023 to 2024 Quarter 4: January to March Overall Initial Failure Rate 15.09% Not set 4.99% Not set 10.10% Not set
2023 to 2024 Quarter 4: January to March Average defects per Initial Test Failure Not set 1.97 Not set 0.42 Not set 1.37
2023 to 2024 Quarter 3: October to December Identification of the vehicle 0.95% 3.18% Not set Not set 0.95% 4.15%
2023 to 2024 Quarter 3: October to December Motorcycle audible warning (Horn) 0.09% 0.29% Not set Not set 0.09% 0.38%
2023 to 2024 Quarter 3: October to December Motorcycle brakes 4.43% 20.18% 1.74% 27.33% 3.19% 17.99%
2023 to 2024 Quarter 3: October to December Motorcycle lamps and reflectors 8.76% 39.10% 1.22% 17.69% 7.95% 45.67%
2023 to 2024 Quarter 3: October to December Motorcycle steering 1.67% 6.33% 0.44% 6.60% 1.31% 6.25%
2023 to 2024 Quarter 3: October to December Motorcycle structure and attachments 2.67% 11.48% 0.64% 10.10% 2.21% 11.90%
2023 to 2024 Quarter 3: October to December Motorcycle suspension 2.28% 9.28% 0.21% 3.21% 2.12% 11.14%
2023 to 2024 Quarter 3: October to December Motorcycle tyres 2.48% 9.38% 2.13% 33.92% 0.39% 1.84%
2023 to 2024 Quarter 3: October to December Motorcycle wheels 0.22% 0.79% 0.08% 1.14% 0.15% 0.69%
2023 to 2024 Quarter 3: October to December Overall Initial Failure Rate 16.17% Not set 5.51% Not set 10.66% Not set
2023 to 2024 Quarter 3: October to December Average defects per Initial Test Failure Not set 1.87 Not set 0.44 Not set 1.43
2023 to 2024 Quarter 2: July to September Identification of the vehicle 1.01% 3.90% Not set Not set 1.01% 4.96%
2023 to 2024 Quarter 2: July to September Motorcycle audible warning (Horn) 0.07% 0.27% Not set Not set 0.07% 0.34%
2023 to 2024 Quarter 2: July to September Motorcycle brakes 3.42% 18.24% 1.26% 24.93% 2.53% 16.41%
2023 to 2024 Quarter 2: July to September Motorcycle lamps and reflectors 7.89% 40.75% 1.01% 18.41% 7.22% 46.85%
2023 to 2024 Quarter 2: July to September Motorcycle steering 1.35% 5.87% 0.36% 6.77% 1.05% 5.63%
2023 to 2024 Quarter 2: July to September Motorcycle structure and attachments 2.30% 11.34% 0.52% 10.23% 1.92% 11.64%
2023 to 2024 Quarter 2: July to September Motorcycle suspension 2.17% 10.15% 0.19% 3.60% 2.02% 11.94%
2023 to 2024 Quarter 2: July to September Motorcycle tyres 2.00% 8.70% 1.72% 34.84% 0.30% 1.56%
2023 to 2024 Quarter 2: July to September Motorcycle wheels 0.19% 0.78% 0.06% 1.22% 0.13% 0.66%
2023 to 2024 Quarter 2: July to September Overall Initial Failure Rate 14.53% Not set 4.48% Not set 10.05% Not set
2023 to 2024 Quarter 2: July to September Average defects per Initial Test Failure Not set 1.79 Not set 0.38 Not set 1.41
2023 to 2024 Quarter 1: April to June Identification of the vehicle 1.08% 4.55% Not set Not set 1.08% 5.78%
2023 to 2024 Quarter 1: April to June Motorcycle audible warning (Horn) 0.07% 0.30% Not set Not set 0.07% 0.38%
2023 to 2024 Quarter 1: April to June Motorcycle brakes 3.02% 17.16% 1.07% 23.19% 2.25% 15.52%
2023 to 2024 Quarter 1: April to June Motorcycle lamps and reflectors 7.76% 42.64% 0.99% 19.73% 7.08% 48.87%
2023 to 2024 Quarter 1: April to June Motorcycle steering 1.12% 5.24% 0.31% 6.43% 0.86% 4.91%
2023 to 2024 Quarter 1: April to June Motorcycle structure and attachments 2.09% 10.93% 0.47% 10.03% 1.73% 11.17%
2023 to 2024 Quarter 1: April to June Motorcycle suspension 1.87% 9.44% 0.16% 3.25% 1.75% 11.12%
2023 to 2024 Quarter 1: April to June Motorcycle tyres 1.90% 9.04% 1.64% 36.32% 0.28% 1.62%
2023 to 2024 Quarter 1: April to June Motorcycle wheels 0.16% 0.72% 0.05% 1.05% 0.11% 0.63%
2023 to 2024 Quarter 1: April to June Overall Initial Failure Rate 13.90% Not set 4.16% Not set 9.74% Not set
2023 to 2024 Quarter 1: April to June Average defects per Initial Test Failure Not set 1.73 Not set 0.37 Not set 1.36
2022 to 2023 Total Identification of the vehicle 1.09% 4.04% Not set Not set 1.09% 5.15%
2022 to 2023 Total Motorcycle audible warning (Horn) 0.08% 0.29% Not set Not set 0.08% 0.37%
2022 to 2023 Total Motorcycle brakes 3.53% 17.91% 1.33% 25.25% 2.59% 15.90%
2022 to 2023 Total Motorcycle lamps and reflectors 8.42% 41.44% 0.94% 16.41% 7.79% 48.28%
2022 to 2023 Total Motorcycle steering 1.35% 5.61% 0.35% 6.41% 1.06% 5.38%
2022 to 2023 Total Motorcycle structure and attachments 2.40% 11.24% 0.57% 10.63% 1.98% 11.41%
2022 to 2023 Total Motorcycle suspension 2.12% 9.56% 0.19% 3.37% 1.97% 11.25%
2022 to 2023 Total Motorcycle tyres 2.19% 9.19% 1.89% 36.79% 0.32% 1.64%
2022 to 2023 Total Motorcycle wheels 0.18% 0.73% 0.06% 1.14% 0.12% 0.61%
2022 to 2023 Total Overall Initial Failure Rate 15.18% Not set 4.67% Not set 10.51% Not set
2022 to 2023 Total Average defects per Initial Test Failure Not set 1.8 Not set 0.39 Not set 1.41
2022 to 2023 Quarter 4: January to March Identification of the vehicle 1.13% 4.11% Not set Not set 1.13% 5.32%
2022 to 2023 Quarter 4: January to March Motorcycle audible warning (Horn) 0.09% 0.31% Not set Not set 0.09% 0.40%
2022 to 2023 Quarter 4: January to March Motorcycle brakes 3.85% 19.04% 1.50% 26.40% 2.79% 16.87%
2022 to 2023 Quarter 4: January to March Motorcycle lamps and reflectors 8.57% 40.95% 1.13% 18.24% 7.81% 47.63%
2022 to 2023 Quarter 4: January to March Motorcycle steering 1.41% 5.78% 0.38% 6.28% 1.09% 5.63%
2022 to 2023 Quarter 4: January to March Motorcycle structure and attachments 2.49% 11.51% 0.63% 10.69% 2.03% 11.76%
2022 to 2023 Quarter 4: January to March Motorcycle suspension 1.96% 8.56% 0.19% 3.14% 1.81% 10.15%
2022 to 2023 Quarter 4: January to March Motorcycle tyres 2.22% 9.09% 1.92% 34.34% 0.33% 1.66%
2022 to 2023 Quarter 4: January to March Motorcycle wheels 0.17% 0.66% 0.06% 0.91% 0.12% 0.59%
2022 to 2023 Quarter 4: January to March Overall Initial Failure Rate 15.54% Not set 5.02% Not set 10.52% Not set
2022 to 2023 Quarter 4: January to March Average defects per Initial Test Failure Not set 1.8 Not set 0.41 Not set 1.39
2022 to 2023 Quarter 3: October to December Identification of the vehicle 1.01% 3.39% Not set Not set 1.01% 4.43%
2022 to 2023 Quarter 3: October to December Motorcycle audible warning (Horn) 0.08% 0.27% Not set Not set 0.08% 0.35%
2022 to 2023 Quarter 3: October to December Motorcycle brakes 4.23% 19.50% 1.70% 26.63% 3.02% 17.32%
2022 to 2023 Quarter 3: October to December Motorcycle lamps and reflectors 8.82% 39.47% 1.21% 17.54% 8.00% 46.19%
2022 to 2023 Quarter 3: October to December Motorcycle steering 1.64% 6.12% 0.41% 6.21% 1.30% 6.09%
2022 to 2023 Quarter 3: October to December Motorcycle structure and attachments 2.70% 11.52% 0.63% 9.70% 2.24% 12.08%
2022 to 2023 Quarter 3: October to December Motorcycle suspension 2.28% 9.32% 0.23% 3.39% 2.10% 11.13%
2022 to 2023 Quarter 3: October to December Motorcycle tyres 2.56% 9.65% 2.22% 35.41% 0.37% 1.75%
2022 to 2023 Quarter 3: October to December Motorcycle wheels 0.22% 0.77% 0.07% 1.12% 0.14% 0.66%
2022 to 2023 Quarter 3: October to December Overall Initial Failure Rate 16.23% Not set 5.57% Not set 10.66% Not set
2022 to 2023 Quarter 3: October to December Average defects per Initial Test Failure Not set 1.87 Not set 0.44 Not set 1.43
2022 to 2023 Quarter 2: July to September Identification of the vehicle 0.99% 3.76% Not set Not set 0.99% 4.75%
2022 to 2023 Quarter 2: July to September Motorcycle audible warning (Horn) 0.07% 0.28% Not set Not set 0.07% 0.35%
2022 to 2023 Quarter 2: July to September Motorcycle brakes 3.36% 17.38% 1.25% 24.81% 2.48% 15.42%
2022 to 2023 Quarter 2: July to September Motorcycle lamps and reflectors 8.24% 41.64% 0.84% 15.30% 7.67% 48.57%
2022 to 2023 Quarter 2: July to September Motorcycle steering 1.33% 5.65% 0.36% 6.79% 1.03% 5.35%
2022 to 2023 Quarter 2: July to September Motorcycle structure and attachments 2.31% 10.95% 0.55% 10.73% 1.90% 11.01%
2022 to 2023 Quarter 2: July to September Motorcycle suspension 2.25% 10.42% 0.18% 3.42% 2.11% 12.26%
2022 to 2023 Quarter 2: July to September Motorcycle tyres 2.15% 9.22% 1.85% 37.85% 0.33% 1.69%
2022 to 2023 Quarter 2: July to September Motorcycle wheels 0.17% 0.71% 0.06% 1.11% 0.12% 0.60%
2022 to 2023 Quarter 2: July to September Overall Initial Failure Rate 14.87% Not set 4.48% Not set 10.39% Not set
2022 to 2023 Quarter 2: July to September Average defects per Initial Test Failure Not set 1.8 Not set 0.37 Not set 1.42
2022 to 2023 Quarter 1: April to June Identification of the vehicle 1.18% 4.56% Not set Not set 1.18% 5.72%
2022 to 2023 Quarter 1: April to June Motorcycle audible warning (Horn) 0.08% 0.30% Not set Not set 0.08% 0.38%
2022 to 2023 Quarter 1: April to June Motorcycle brakes 3.19% 16.90% 1.15% 24.11% 2.38% 15.07%
2022 to 2023 Quarter 1: April to June Motorcycle lamps and reflectors 8.34% 42.51% 0.81% 15.49% 7.80% 49.40%
2022 to 2023 Quarter 1: April to June Motorcycle steering 1.22% 5.21% 0.31% 6.29% 0.95% 4.94%
2022 to 2023 Quarter 1: April to June Motorcycle structure and attachments 2.30% 11.19% 0.53% 11.01% 1.90% 11.24%
2022 to 2023 Quarter 1: April to June Motorcycle suspension 2.02% 9.55% 0.17% 3.46% 1.89% 11.10%
2022 to 2023 Quarter 1: April to June Motorcycle tyres 2.05% 9.00% 1.78% 38.30% 0.29% 1.53%
2022 to 2023 Quarter 1: April to June Motorcycle wheels 0.19% 0.76% 0.07% 1.35% 0.12% 0.62%
2022 to 2023 Quarter 1: April to June Overall Initial Failure Rate 14.80% Not set 4.26% Not set 10.53% Not set
2022 to 2023 Quarter 1: April to June Average defects per Initial Test Failure Not set 1.77 Not set 0.36 Not set 0.01
2021 to 2022 Total Identification of the vehicle 1.11% 3.92% Not set Not set 1.11% 4.95%
2021 to 2022 Total Motorcycle audible warning (Horn) 0.47% 1.65% Not set Not set 0.47% 2.08%
2021 to 2022 Total Motorcycle brakes 3.67% 17.59% 1.36% 25.21% 2.70% 15.59%
2021 to 2022 Total Motorcycle lamps and reflectors 8.72% 41.21% 0.82% 13.98% 8.18% 48.35%
2021 to 2022 Total Motorcycle steering 1.39% 5.51% 0.36% 6.53% 1.09% 5.24%
2021 to 2022 Total Motorcycle structure and attachments 2.48% 11.00% 0.62% 11.36% 2.03% 10.90%
2021 to 2022 Total Motorcycle suspension 2.17% 9.23% 0.21% 3.86% 2.00% 10.63%
2021 to 2022 Total Motorcycle tyres 2.27% 9.07% 1.95% 37.49% 0.34% 1.63%
2021 to 2022 Total Motorcycle wheels 0.22% 0.82% 0.09% 1.57% 0.13% 0.62%
2021 to 2022 Total Overall Initial Failure Rate 15.52% Not set 4.73% Not set 10.79% Not set
2021 to 2022 Total Average defects per Initial Test Failure Not set 1.85 Not set 0.38 Not set 1.47
2021 to 2022 Quarter 4: January to March Identification of the vehicle 1.16% 4.16% Not set Not set 1.16% 5.32%
2021 to 2022 Quarter 4: January to March Lamps, reflectors and electrical equipment 0.00% 0.00% Not set Not set 0.00% 0.00%
2021 to 2022 Quarter 4: January to March Motorcycle audible warning (Horn) 0.09% 0.31% Not set Not set 0.09% 0.40%
2021 to 2022 Quarter 4: January to March Motorcycle brakes 3.75% 18.28% 1.45% 26.14% 2.72% 16.09%
2021 to 2022 Quarter 4: January to March Motorcycle lamps and reflectors 8.74% 41.43% 0.86% 14.13% 8.18% 49.04%
2021 to 2022 Quarter 4: January to March Motorcycle steering 1.36% 5.50% 0.37% 6.47% 1.06% 5.23%
2021 to 2022 Quarter 4: January to March Motorcycle structure and attachments 2.54% 11.55% 0.64% 11.45% 2.08% 11.57%
2021 to 2022 Quarter 4: January to March Motorcycle suspension 2.05% 8.82% 0.22% 3.95% 1.88% 10.17%
2021 to 2022 Quarter 4: January to March Motorcycle tyres 2.28% 9.23% 1.98% 36.67% 0.32% 1.58%
2021 to 2022 Quarter 4: January to March Motorcycle wheels 0.20% 0.73% 0.07% 1.20% 0.13% 0.60%
2021 to 2022 Quarter 4: January to March Overall Initial Failure Rate 15.80% Not set 4.90% Not set 10.90% Not set
2021 to 2022 Quarter 4: January to March Average defects per Initial Test Failure Not set 1.79 Not set 0.39 Not set 1.4
2021 to 2022 Quarter 3: October to December Identification of the vehicle 1.02% 3.32% Not set Not set 1.02% 4.29%
2021 to 2022 Quarter 3: October to December Lamps, reflectors and electrical equipment 0.00% 0.00% Not set Not set 0.00% 0.00%
2021 to 2022 Quarter 3: October to December Motorcycle audible warning (Horn) 0.11% 0.36% Not set Not set 0.11% 0.46%
2021 to 2022 Quarter 3: October to December Motorcycle brakes 4.44% 19.76% 1.73% 27.46% 3.18% 17.51%
2021 to 2022 Quarter 3: October to December Motorcycle lamps and reflectors 9.00% 39.05% 0.89% 12.80% 8.41% 46.70%
2021 to 2022 Quarter 3: October to December Motorcycle steering 1.63% 5.92% 0.43% 6.51% 1.29% 5.74%
2021 to 2022 Quarter 3: October to December Motorcycle structure and attachments 2.83% 11.84% 0.74% 11.55% 2.29% 11.92%
2021 to 2022 Quarter 3: October to December Motorcycle suspension 2.37% 9.36% 0.27% 4.05% 2.15% 10.91%
2021 to 2022 Quarter 3: October to December Motorcycle tyres 2.61% 9.55% 2.25% 36.34% 0.39% 1.74%
2021 to 2022 Quarter 3: October to December Motorcycle wheels 0.24% 0.84% 0.09% 1.28% 0.16% 0.71%
2021 to 2022 Quarter 3: October to December Overall Initial Failure Rate 16.60% Not set 5.47% Not set 11.13% Not set
2021 to 2022 Quarter 3: October to December Average defects per Initial Test Failure Not set 1.88 Not set 0.42 Not set 1.45
2021 to 2022 Quarter 2: July to September Identification of the vehicle 1.00% 3.67% Not set Not set 1.00% 4.61%
2021 to 2022 Quarter 2: July to September Lamps, reflectors and electrical equipment 0.00% 0.00% Not set Not set 0.00% 0.00%
2021 to 2022 Quarter 2: July to September Motorcycle audible warning (Horn) 0.55% 2.00% Not set Not set 0.55% 2.50%
2021 to 2022 Quarter 2: July to September Motorcycle brakes 3.47% 17.27% 1.26% 24.92% 2.56% 15.32%
2021 to 2022 Quarter 2: July to September Motorcycle lamps and reflectors 8.28% 40.94% 0.75% 13.71% 7.78% 47.87%
2021 to 2022 Quarter 2: July to September Motorcycle steering 1.34% 5.52% 0.35% 6.69% 1.05% 5.22%
2021 to 2022 Quarter 2: July to September Motorcycle structure and attachments 2.38% 10.93% 0.57% 11.32% 1.96% 10.84%
2021 to 2022 Quarter 2: July to September Motorcycle suspension 2.24% 9.98% 0.21% 4.01% 2.08% 11.50%
2021 to 2022 Quarter 2: July to September Motorcycle tyres 2.12% 8.87% 1.83% 37.59% 0.32% 1.57%
2021 to 2022 Quarter 2: July to September Motorcycle wheels 0.21% 0.82% 0.09% 1.76% 0.12% 0.58%
2021 to 2022 Quarter 2: July to September Overall Initial Failure Rate 14.79% Not set 4.46% Not set 10.33% Not set
2021 to 2022 Quarter 2: July to September Average defects per Initial Test Failure Not set 1.87 Not set 0.38 Not set 1.49
2021 to 2022 Quarter 1: April to June Identification of the vehicle 1.23% 4.29% Not set Not set 1.23% 5.33%
2021 to 2022 Quarter 1: April to June Lamps, reflectors and electrical equipment 0.00% 0.00% Not set Not set 0.00% 0.00%
2021 to 2022 Quarter 1: April to June Motorcycle audible warning (Horn) 0.85% 2.94% Not set Not set 0.85% 3.66%
2021 to 2022 Quarter 1: April to June Motorcycle brakes 3.43% 16.25% 1.19% 23.39% 2.58% 14.52%
2021 to 2022 Quarter 1: April to June Motorcycle lamps and reflectors 8.97% 42.45% 0.82% 14.84% 8.43% 49.15%
2021 to 2022 Quarter 1: April to June Motorcycle steering 1.35% 5.29% 0.34% 6.43% 1.06% 5.01%
2021 to 2022 Quarter 1: April to June Motorcycle structure and attachments 2.36% 10.22% 0.58% 11.19% 1.93% 9.99%
2021 to 2022 Quarter 1: April to June Motorcycle suspension 2.09% 8.79% 0.19% 3.55% 1.95% 10.06%
2021 to 2022 Quarter 1: April to June Motorcycle tyres 2.23% 8.89% 1.90% 38.75% 0.35% 1.65%
2021 to 2022 Quarter 1: April to June Motorcycle wheels 0.23% 0.86% 0.10% 1.85% 0.13% 0.62%
2021 to 2022 Quarter 1: April to June Overall Initial Failure Rate 15.47% Not set 4.53% Not set 10.94% Not set
2021 to 2022 Quarter 1: April to June Average defects per Initial Test Failure Not set 1.87 Not set 0.37 Not set 1.51
2020 to 2021 Total Identification of the vehicle 1.11% 3.72% Not set Not set 1.11% 4.69%
2020 to 2021 Total Motorcycle audible warning (Horn) 0.90% 2.97% Not set Not set 0.90% 3.74%
2020 to 2021 Total Motorcycle brakes 3.93% 17.98% 1.56% 27.72% 2.81% 15.42%
2020 to 2021 Total Motorcycle lamps and reflectors 8.76% 39.60% 0.52% 8.52% 8.41% 47.75%
2020 to 2021 Total Motorcycle steering 1.47% 5.49% 0.37% 6.27% 1.16% 5.29%
2020 to 2021 Total Motorcycle structure and attachments 2.60% 10.98% 0.69% 12.04% 2.09% 10.70%
2020 to 2021 Total Motorcycle suspension 2.18% 8.83% 0.23% 3.84% 2.00% 10.14%
2020 to 2021 Total Motorcycle tyres 2.48% 9.46% 2.17% 39.58% 0.34% 1.57%
2020 to 2021 Total Motorcycle wheels 0.27% 0.97% 0.12% 2.03% 0.15% 0.69%
2020 to 2021 Total Overall Initial Failure Rate 15.87% Not set 4.94% Not set 10.93% Not set
2020 to 2021 Total Average defects per Initial Test Failure Not set 1.9 Not set 0.4 Not set 1.51
2020 to 2021 Quarter 4: January to March Identification of the vehicle 1.27% 4.09% Not set Not set 1.27% 5.23%
2020 to 2021 Quarter 4: January to March Lamps, reflectors and electrical equipment 0.00% 0.00% Not set Not set 0.00% 0.00%
2020 to 2021 Quarter 4: January to March Motorcycle audible warning (Horn) 0.94% 2.96% Not set Not set 0.94% 3.79%
2020 to 2021 Quarter 4: January to March Motorcycle brakes 4.14% 18.29% 1.71% 27.77% 2.94% 15.63%
2020 to 2021 Quarter 4: January to March Motorcycle lamps and reflectors 9.33% 40.58% 0.91% 13.47% 8.74% 48.16%
2020 to 2021 Quarter 4: January to March Motorcycle steering 1.45% 5.18% 0.38% 5.91% 1.13% 4.98%
2020 to 2021 Quarter 4: January to March Motorcycle structure and attachments 2.74% 11.06% 0.73% 11.63% 2.20% 10.90%
2020 to 2021 Quarter 4: January to March Motorcycle suspension 2.02% 7.88% 0.22% 3.32% 1.85% 9.15%
2020 to 2021 Quarter 4: January to March Motorcycle tyres 2.52% 9.14% 2.20% 36.37% 0.34% 1.51%
2020 to 2021 Quarter 4: January to March Motorcycle wheels 0.24% 0.83% 0.10% 1.53% 0.15% 0.64%
2020 to 2021 Quarter 4: January to March Overall Initial Failure Rate 16.45% Not set 5.38% Not set 11.06% Not set
2020 to 2021 Quarter 4: January to March Average defects per Initial Test Failure Not set 1.92 Not set 0.42 Not set 1.5
2020 to 2021 Quarter 3: October to December Identification of the vehicle 1.13% 3.34% Not set Not set 1.13% 4.27%
2020 to 2021 Quarter 3: October to December Lamps, reflectors and electrical equipment 0.00% 0.00% Not set Not set 0.00% 0.00%
2020 to 2021 Quarter 3: October to December Motorcycle audible warning (Horn) 0.90% 2.64% Not set Not set 0.90% 3.38%
2020 to 2021 Quarter 3: October to December Motorcycle brakes 4.64% 18.58% 1.95% 29.38% 3.19% 15.60%
2020 to 2021 Quarter 3: October to December Motorcycle lamps and reflectors 9.58% 38.48% 0.47% 6.51% 9.27% 47.33%
2020 to 2021 Quarter 3: October to December Motorcycle steering 1.81% 6.00% 0.45% 6.42% 1.44% 5.88%
2020 to 2021 Quarter 3: October to December Motorcycle structure and attachments 3.04% 11.60% 0.82% 12.29% 2.46% 11.41%
2020 to 2021 Quarter 3: October to December Motorcycle suspension 2.36% 8.46% 0.27% 3.92% 2.13% 9.71%
2020 to 2021 Quarter 3: October to December Motorcycle tyres 2.96% 9.90% 2.58% 39.60% 0.41% 1.69%
2020 to 2021 Quarter 3: October to December Motorcycle wheels 0.31% 0.99% 0.13% 1.89% 0.18% 0.74%
2020 to 2021 Quarter 3: October to December Overall Initial Failure Rate 17.55% Not set 5.79% Not set 11.76% Not set
2020 to 2021 Quarter 3: October to December Average defects per Initial Test Failure Not set 1.95 Not set 0.42 Not set 1.53
2020 to 2021 Quarter 2: July to September Identification of the vehicle 0.99% 3.52% Not set Not set 0.99% 4.38%
2020 to 2021 Quarter 2: July to September Lamps, reflectors and electrical equipment 0.00% 0.00% Not set Not set 0.00% 0.00%
2020 to 2021 Quarter 2: July to September Motorcycle audible warning (Horn) 0.85% 2.99% Not set Not set 0.85% 3.73%
2020 to 2021 Quarter 2: July to September Motorcycle brakes 3.66% 17.83% 1.37% 27.11% 2.67% 15.54%
2020 to 2021 Quarter 2: July to September Motorcycle lamps and reflectors 8.20% 39.13% 0.36% 6.49% 7.95% 47.20%
2020 to 2021 Quarter 2: July to September Motorcycle steering 1.42% 5.61% 0.36% 6.80% 1.11% 5.31%
2020 to 2021 Quarter 2: July to September Motorcycle structure and attachments 2.47% 11.03% 0.63% 12.28% 2.00% 10.72%
2020 to 2021 Quarter 2: July to September Motorcycle suspension 2.24% 9.59% 0.21% 4.02% 2.08% 10.97%
2020 to 2021 Quarter 2: July to September Motorcycle tyres 2.28% 9.29% 2.01% 40.99% 0.30% 1.46%
2020 to 2021 Quarter 2: July to September Motorcycle wheels 0.27% 1.02% 0.12% 2.31% 0.15% 0.70%
2020 to 2021 Quarter 2: July to September Overall Initial Failure Rate 15.10% Not set 4.46% Not set 10.64% Not set
2020 to 2021 Quarter 2: July to September Average defects per Initial Test Failure Not set 1.88 Not set 0.37 Not set 1.51
2020 to 2021 Quarter 1: April to June Identification of the vehicle 1.08% 3.97% Not set Not set 1.08% 4.94%
2020 to 2021 Quarter 1: April to June Lamps, reflectors and electrical equipment 0.00% 0.00% Not set Not set 0.00% 0.00%
2020 to 2021 Quarter 1: April to June Motorcycle audible warning (Horn) 0.91% 3.31% Not set Not set 0.91% 4.12%
2020 to 2021 Quarter 1: April to June Motorcycle brakes 3.44% 17.10% 1.30% 26.49% 2.50% 14.79%
2020 to 2021 Quarter 1: April to June Motorcycle lamps and reflectors 8.15% 40.31% 0.37% 7.01% 7.90% 48.50%
2020 to 2021 Quarter 1: April to June Motorcycle steering 1.27% 5.16% 0.30% 5.82% 1.01% 5.00%
2020 to 2021 Quarter 1: April to June Motorcycle structure and attachments 2.24% 10.11% 0.60% 11.92% 1.78% 9.67%
2020 to 2021 Quarter 1: April to June Motorcycle suspension 2.11% 9.36% 0.22% 4.21% 1.94% 10.62%
2020 to 2021 Quarter 1: April to June Motorcycle tyres 2.29% 9.64% 1.99% 42.03% 0.33% 1.66%
2020 to 2021 Quarter 1: April to June Motorcycle wheels 0.26% 1.05% 0.13% 2.52% 0.14% 0.69%
2020 to 2021 Quarter 1: April to June Overall Initial Failure Rate 14.80% Not set 11.20% Not set 25.20% Not set
2020 to 2021 Quarter 1: April to June Average defects per Initial Test Failure Not set 1.87 Not set 0.37 Not set 1.5
2019 to 2020 Total Identification of the vehicle 1.15% 3.66% Not set Not set 1.15% 4.61%
2019 to 2020 Total Motorcycle audible warning (Horn) 0.90% 2.85% Not set Not set 0.90% 3.59%
2019 to 2020 Total Motorcycle brakes 4.13% 17.77% 1.70% 28.90% 2.88% 14.86%
2019 to 2020 Total Motorcycle lamps and reflectors 9.20% 39.40% 0.39% 6.10% 8.94% 48.10%
2019 to 2020 Total Motorcycle steering 1.61% 5.74% 0.38% 6.11% 1.30% 5.64%
2019 to 2020 Total Motorcycle structure and attachments 2.77% 11.22% 0.73% 12.34% 2.24% 10.93%
2019 to 2020 Total Motorcycle suspension 2.28% 8.82% 0.24% 3.88% 2.09% 10.11%
2019 to 2020 Total Motorcycle tyres 2.64% 9.60% 2.34% 40.66% 0.34% 1.48%
2019 to 2020 Total Motorcycle wheels 0.28% 0.95% 0.13% 2.01% 0.16% 0.68%
2019 to 2020 Total Overall Initial Failure Rate 16.74% Not set 5.16% Not set 11.58% Not set
2019 to 2020 Total Average defects per Initial Test Failure Not set 1.9 Not set 0.39 Not set 1.5
2019 to 2020 Quarter 4: January to March Brakes 0.00% 0.01% 0.00% 0.02% 0.00% 0.01%
2019 to 2020 Quarter 4: January to March Identification of the vehicle 0.82% 3.49% 0.00% 0.00% 1.13% 4.43%
2019 to 2020 Quarter 4: January to March Lamps, reflectors and electrical equipment 0.00% 0.00% 0.00% 0.01% 0.00% 0.00%
2019 to 2020 Quarter 4: January to March Motorcycle audible warning (Horn) 0.73% 2.96% 0.00% 0.00% 0.97% 3.76%
2019 to 2020 Quarter 4: January to March Motorcycle brakes 3.61% 19.22% 2.00% 32.45% 3.09% 15.65%
2019 to 2020 Quarter 4: January to March Motorcycle lamps and reflectors 7.25% 39.07% 0.42% 6.23% 9.09% 47.93%
2019 to 2020 Quarter 4: January to March Motorcycle steering 1.41% 5.72% 0.39% 6.01% 1.32% 5.64%
2019 to 2020 Quarter 4: January to March Motorcycle structure and attachments 2.36% 11.61% 0.77% 12.16% 2.38% 11.46%
2019 to 2020 Quarter 4: January to March Motorcycle suspension 1.77% 7.81% 0.24% 3.73% 1.90% 8.90%
2019 to 2020 Quarter 4: January to March Motorcycle tyres 2.17% 9.26% 2.30% 37.81% 0.36% 1.56%
2019 to 2020 Quarter 4: January to March Motorcycle wheels 0.26% 0.86% 0.11% 1.58% 0.16% 0.67%
2019 to 2020 Quarter 4: January to March Overall Initial Failure Rate 16.90% Not set 5.40% Not set 11.50% Not set
2019 to 2020 Quarter 4: January to March Average defects per Initial Test Failure Not set 1.93 Not set 0.41 Not set 1.52
2019 to 2020 Quarter 3: October to December Brakes 0.10% 0.00% 0.00% 0.00% 0.10% 0.00%
2019 to 2020 Quarter 3: October to December Identification of the vehicle 1.20% 3.20% 0.00% 0.00% 1.20% 4.00%
2019 to 2020 Quarter 3: October to December Lamps, reflectors and electrical equipment 0.20% 0.00% 0.00% 0.00% 0.20% 0.00%
2019 to 2020 Quarter 3: October to December Motorcycle audible warning (Horn) 1.10% 2.80% 0.00% 0.00% 1.10% 3.50%
2019 to 2020 Quarter 3: October to December Motorcycle brakes 5.30% 19.00% 2.30% 30.80% 3.70% 15.70%
2019 to 2020 Quarter 3: October to December Motorcycle lamps and reflectors 10.70% 38.30% 0.50% 6.20% 10.40% 47.10%
2019 to 2020 Quarter 3: October to December Motorcycle steering 2.10% 6.10% 0.50% 6.10% 1.70% 6.10%
2019 to 2020 Quarter 3: October to December Motorcycle structure and attachments 3.50% 11.90% 1.00% 12.80% 2.80% 11.60%
2019 to 2020 Quarter 3: October to December Motorcycle suspension 2.60% 8.40% 0.30% 4.00% 2.40% 9.60%
2019 to 2020 Quarter 3: October to December Motorcycle tyres 3.20% 9.50% 2.80% 38.00% 0.40% 1.60%
2019 to 2020 Quarter 3: October to December Motorcycle wheels 0.40% 1.10% 0.20% 2.20% 0.20% 0.80%
2019 to 2020 Quarter 3: October to December Overall Initial Failure Rate 19.20% Not set 6.40% Not set 12.80% Not set
2019 to 2020 Quarter 3: October to December Average defects per Initial Test Failure Not set 2.02 Not set 0.44 Not set 1.59
2019 to 2020 Quarter 2: July to September Brakes 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
2019 to 2020 Quarter 2: July to September Identification of the vehicle 1.10% 3.50% 0.00% 0.00% 1.10% 4.40%
2019 to 2020 Quarter 2: July to September Motorcycle audible warning (Horn) 0.90% 2.80% 0.00% 0.00% 0.90% 3.50%
2019 to 2020 Quarter 2: July to September Motorcycle brakes 4.10% 17.40% 1.60% 28.00% 2.90% 14.70%
2019 to 2020 Quarter 2: July to September Motorcycle lamps and reflectors 9.20% 39.20% 0.40% 6.10% 9.00% 47.60%
2019 to 2020 Quarter 2: July to September Motorcycle steering 1.70% 5.90% 0.40% 6.40% 1.30% 5.70%
2019 to 2020 Quarter 2: July to September Motorcycle structure and attachments 2.80% 11.20% 0.70% 12.60% 2.30% 10.80%
2019 to 2020 Quarter 2: July to September Motorcycle suspension 2.50% 9.60% 0.20% 3.90% 2.30% 11.00%
2019 to 2020 Quarter 2: July to September Motorcycle tyres 2.60% 9.50% 2.30% 40.90% 0.40% 1.50%
2019 to 2020 Quarter 2: July to September Motorcycle wheels 0.30% 1.00% 0.10% 2.10% 0.20% 0.70%
2019 to 2020 Quarter 2: July to September Overall Initial Failure Rate 16.80% Not set 5.10% Not set 11.70% Not set
2019 to 2020 Quarter 2: July to September Average defects per Initial Test Failure Not set 1.91 Not set 0.39 Not set 1.52
2019 to 2020 Quarter 1: April to June Brakes 0.00% 0.00% 0.00% 0.01% 0.00% 0.00%
2019 to 2020 Quarter 1: April to June Identification of the vehicle 1.17% 4.09% 0.00% 0.00% 1.17% 5.14%
2019 to 2020 Quarter 1: April to June Lamps, reflectors and electrical equipment 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
2019 to 2020 Quarter 1: April to June Motorcycle audible warning (Horn) 0.82% 2.86% 0.00% 0.00% 0.82% 3.60%
2019 to 2020 Quarter 1: April to June Motorcycle brakes 3.60% 16.83% 1.43% 26.88% 2.52% 14.24%
2019 to 2020 Quarter 1: April to June Motorcycle lamps and reflectors 8.64% 40.21% 0.35% 6.02% 8.40% 49.04%
2019 to 2020 Quarter 1: April to June Motorcycle steering 1.41% 5.50% 0.33% 5.96% 1.14% 5.39%
2019 to 2020 Quarter 1: April to June Motorcycle structure and attachments 2.47% 10.77% 0.65% 12.02% 1.98% 10.45%
2019 to 2020 Quarter 1: April to June Motorcycle suspension 2.09% 8.85% 0.21% 3.89% 1.93% 10.13%
2019 to 2020 Quarter 1: April to June Motorcycle tyres 2.48% 9.95% 2.22% 43.18% 0.29% 1.37%
2019 to 2020 Quarter 1: April to June Motorcycle wheels 0.25% 0.93% 0.12% 2.05% 0.14% 0.64%
2019 to 2020 Quarter 1: April to June Overall Initial Failure Rate 15.83% Not set 4.71% Not set 11.12% Not set
2019 to 2020 Quarter 1: April to June Average defects per Initial Test Failure Not set 1.8 Not set 0.4 Not set 1.4
2018 to 2019 20 May 2018 to 31 March 2019 Motorcycle lamps and reflectors 7.20% 38.80% 0.30% 6.10% 7.00% 47.00%
2018 to 2019 20 May 2018 to 31 March 2019 Motorcycle brakes 3.40% 18.00% 1.30% 28.90% 2.40% 15.30%
2018 to 2019 20 May 2018 to 31 March 2019 Motorcycle structure and attachments 2.30% 11.80% 0.60% 12.40% 1.90% 11.70%
2018 to 2019 20 May 2018 to 31 March 2019 Motorcycle tyres 2.00% 8.90% 1.70% 37.20% 0.30% 1.80%
2018 to 2019 20 May 2018 to 31 March 2019 Motorcycle suspension 1.90% 9.10% 0.20% 4.20% 1.70% 10.30%
2018 to 2019 20 May 2018 to 31 March 2019 Motorcycle steering 1.30% 5.90% 0.40% 8.40% 1.00% 5.20%
2018 to 2019 20 May 2018 to 31 March 2019 Identification of the vehicle 0.90% 3.60% Not set Not set 0.90% 4.50%
2018 to 2019 20 May 2018 to 31 March 2019 Motorcycle audible warning (Horn) 0.70% 2.80% Not set Not set 0.70% 3.50%
2018 to 2019 20 May 2018 to 31 March 2019 Motorcycle wheels 0.20% 1.00% 0.10% 2.80% 0.10% 0.60%
2018 to 2019 20 May 2018 to 31 March 2019 Brakes 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
2018 to 2019 20 May 2018 to 31 March 2019 Lamps, reflectors and electrical equipment 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
2018 to 2019 20 May 2018 to 31 March 2019 Road Wheels 0.00% 0.00% Not set Not set Not set Not set
2018 to 2019 20 May 2018 to 31 March 2019 Tyres 0.00% 0.00% 0.00% 0.00% Not set Not set
2018 to 2019 20 May 2018 to 31 March 2019 Overall Initial Failure Rate 17.30% Not set 5.30% Not set 12.10% Not set
2018 to 2019 20 May 2018 to 31 March 2019 Average defects per Initial Test Failure Not set 1.5 Not set 0.3 Not set 1.2
2018 to 2019 1 April 2018 to 19 May 2018 Body and structure 0.60% 2.60% Not set Not set Not set Not set
2018 to 2019 1 April 2018 to 19 May 2018 Brakes 4.00% 18.60% Not set Not set Not set Not set
2018 to 2019 1 April 2018 to 19 May 2018 Drive system 1.20% 4.90% Not set Not set Not set Not set
2018 to 2019 1 April 2018 to 19 May 2018 Driving controls 0.40% 1.30% Not set Not set Not set Not set
2018 to 2019 1 April 2018 to 19 May 2018 Fuel and exhaust 0.80% 2.80% Not set Not set Not set Not set
2018 to 2019 1 April 2018 to 19 May 2018 Lighting and signalling 8.60% 40.00% Not set Not set Not set Not set
2018 to 2019 1 April 2018 to 19 May 2018 Reg plates and VIN 1.10% 4.60% Not set Not set Not set Not set
2018 to 2019 1 April 2018 to 19 May 2018 Sidecar 0.00% 0.00% Not set Not set Not set Not set
2018 to 2019 1 April 2018 to 19 May 2018 Steering and suspension 3.20% 14.40% Not set Not set Not set Not set
2018 to 2019 1 April 2018 to 19 May 2018 Tyres and wheels 2.70% 10.70% Not set Not set Not set Not set
2018 to 2019 1 April 2018 to 19 May 2018 Overall Initial Failure Rate 15.60% Not set Not set Not set Not set Not set
2018 to 2019 1 April 2018 to 19 May 2018 Average defects per Initial Test Failure Not set 1.88 Not set Not set Not set Not set
2017 to 2018 Not set Body and structure 0.70% 2.60% Not set Not set Not set Not set
2017 to 2018 Not set Brakes 4.60% 18.80% Not set Not set Not set Not set
2017 to 2018 Not set Drive system 1.40% 5.10% Not set Not set Not set Not set
2017 to 2018 Not set Driving controls 0.45% 1.30% Not set Not set Not set Not set
2017 to 2018 Not set Fuel and exhaust 0.90% 3.00% Not set Not set Not set Not set
2017 to 2018 Not set Lighting and signalling 9.50% 40.00% Not set Not set Not set Not set
2017 to 2018 Not set Reg plates and VIN 1.10% 4.00% Not set Not set Not set Not set
2017 to 2018 Not set Sidecar 0.00% 0.00% Not set Not set Not set Not set
2017 to 2018 Not set Steering and suspension 3.80% 14.80% Not set Not set Not set Not set
2017 to 2018 Not set Tyres and wheels 3.10% 10.90% Not set Not set Not set Not set
2017 to 2018 Not set Overall Initial Failure Rate 17.10% Not set Not set Not set Not set Not set
2017 to 2018 Not set Average defects per Initial Test Failure Not set 1.97 Not set Not set Not set Not set
2016 to 2017 Not set Body and structure 0.80% 2.50% Not set Not set Not set Not set
2016 to 2017 Not set Brakes 4.80% 18.60% Not set Not set Not set Not set
2016 to 2017 Not set Drive system 1.40% 5.00% Not set Not set Not set Not set
2016 to 2017 Not set Driving controls 0.40% 1.30% Not set Not set Not set Not set
2016 to 2017 Not set Fuel and exhaust 1.00% 3.10% Not set Not set Not set Not set
2016 to 2017 Not set Lighting and signalling 9.80% 39.40% Not set Not set Not set Not set
2016 to 2017 Not set Reg plates and VIN 1.10% 3.90% Not set Not set Not set Not set
2016 to 2017 Not set Sidecar 0.00% 0.00% Not set Not set Not set Not set
2016 to 2017 Not set Steering and suspension 3.90% 15.00% Not set Not set Not set Not set
2016 to 2017 Not set Tyres and wheels 3.30% 11.20% Not set Not set Not set Not set
2016 to 2017 Not set Overall Initial Failure Rate 17.70% Not set Not set Not set Not set Not set
2016 to 2017 Not set Average defects per Initial Test Failure Not set 1.96 Not set Not set Not set Not set
2015 to 2016 Not set Body and structure 0.80% 2.70% Not set Not set Not set Not set
2015 to 2016 Not set Brakes 4.90% 18.30% Not set Not set Not set Not set
2015 to 2016 Not set Drive system 1.40% 5.00% Not set Not set Not set Not set
2015 to 2016 Not set Driving controls 0.50% 1.30% Not set Not set Not set Not set
2015 to 2016 Not set Fuel and exhaust 1.00% 3.20% Not set Not set Not set Not set
2015 to 2016 Not set Lighting and signalling 10.10% 39.30% Not set Not set Not set Not set
2015 to 2016 Not set Reg plates and VIN 1.10% 3.80% Not set Not set Not set Not set
2015 to 2016 Not set Sidecar 0.00% 0.00% Not set Not set Not set Not set
2015 to 2016 Not set Steering and suspension 4.10% 15.30% Not set Not set Not set Not set
2015 to 2016 Not set Tyres and wheels 3.40% 11.10% Not set Not set Not set Not set
2015 to 2016 Not set Overall Initial Failure Rate 18.20% Not set Not set Not set Not set Not set
2015 to 2016 Not set Average defects per Initial Test Failure Not set 2.01 Not set Not set Not set Not set
2014 to 2015 Not set Body and structure 0.80% 2.80% Not set Not set Not set Not set
2014 to 2015 Not set Brakes 4.80% 18.00% Not set Not set Not set Not set
2014 to 2015 Not set Drive system 1.40% 4.90% Not set Not set Not set Not set
2014 to 2015 Not set Driving controls 0.50% 1.30% Not set Not set Not set Not set
2014 to 2015 Not set Fuel and exhaust 1.10% 3.30% Not set Not set Not set Not set
2014 to 2015 Not set Lighting and signalling 10.00% 39.40% Not set Not set Not set Not set
2014 to 2015 Not set Reg plates and VIN 1.10% 3.70% Not set Not set Not set Not set
2014 to 2015 Not set Sidecar 0.00% 0.00% Not set Not set Not set Not set
2014 to 2015 Not set Steering and suspension 4.10% 15.50% Not set Not set Not set Not set
2014 to 2015 Not set Tyres and wheels 3.40% 10.80% Not set Not set Not set Not set
2014 to 2015 Not set Overall Initial Failure Rate 19.20% Not set Not set Not set Not set Not set
2014 to 2015 Not set Average defects per Initial Test Failure Not set 2.05 Not set Not set Not set Not set
2013 to 2014 Not set Body and structure 0.90% 2.70% Not set Not set Not set Not set
2013 to 2014 Not set Brakes 5.00% 17.90% Not set Not set Not set Not set
2013 to 2014 Not set Drive system 1.40% 4.70% Not set Not set Not set Not set
2013 to 2014 Not set Driving controls 0.40% 1.20% Not set Not set Not set Not set
2013 to 2014 Not set Fuel and exhaust 1.10% 3.30% Not set Not set Not set Not set
2013 to 2014 Not set Lighting and signalling 10.40% 39.60% Not set Not set Not set Not set
2013 to 2014 Not set Reg plates and VIN 1.20% 3.80% Not set Not set Not set Not set
2013 to 2014 Not set Sidecar 0.00% 0.00% Not set Not set Not set Not set
2013 to 2014 Not set Steering and suspension 4.30% 15.60% Not set Not set Not set Not set
2013 to 2014 Not set Tyres and wheels 3.50% 10.70% Not set Not set Not set Not set
2013 to 2014 Not set Overall Initial Failure Rate 19.90% - Not set Not set Not set Not set
2013 to 2014 Not set Average defects per Initial Test Failure - 2.06 Not set Not set Not set Not set