Research and analysis

Table 7: ACM remediation progress by date identified with unsafe ACM cladding and tenure, 31 January 2023

Updated 16 February 2023
Download CSV 1.83 KB

Date identified with unsafe ACM cladding Tenure Remediation completed Works complete awaiting building control signoff Remediation started - cladding removed Remediation started Plans in place Responded with intent Remediation plan unclear / Awaiting further advice
Identified by 31 December 2019 Social sector residential 118 17 19 0 0 0 0
Identified by 31 December 2019 Private sector residential 142 20 11 9 5 0 0
Identified by 31 December 2019 Student accommodation 49 2 1 0 0 0 0
Identified by 31 December 2019 Hotels 21 2 1 2 0 1 0
Identified by 31 December 2019 Publicly-owned buildings 7 0 0 1 0 0 0
Identified by 31 December 2019 All tenures 337 41 32 12 5 1 0
Identified by 31 December 2020 Social sector residential 119 18 19 0 0 0 0
Identified by 31 December 2020 Private sector residential 155 23 13 13 7 1 0
Identified by 31 December 2020 Student accommodation 50 3 1 0 0 0 0
Identified by 31 December 2020 Hotels 21 3 1 3 0 1 0
Identified by 31 December 2020 Publicly-owned buildings 7 0 0 1 0 0 0
Identified by 31 December 2020 All tenures 352 47 34 17 7 2 0
Identified by 31 December 2021 Social sector residential 120 18 21 1 0 0 0
Identified by 31 December 2021 Private sector residential 157 25 13 15 10 6 0
Identified by 31 December 2021 Student accommodation 50 3 1 1 1 0 0
Identified by 31 December 2021 Hotels 22 3 1 3 0 2 0
Identified by 31 December 2021 Publicly-owned buildings 7 0 0 1 0 0 0
Identified by 31 December 2021 All tenures 356 49 36 21 11 8 0
All buildings identified Social sector residential 120 18 21 1 0 0 0
All buildings identified Private sector residential 158 26 13 15 11 7 3
All buildings identified Student accommodation 50 3 1 1 1 0 0
All buildings identified Hotels 22 3 1 3 0 2 0
All buildings identified Publicly-owned buildings 7 0 0 1 0 0 0
All buildings identified All tenures 357 50 36 21 12 9 3