Table 7: ACM remediation progress by date identified with unsafe ACM cladding and tenure, 30 September 2022

Updated 13 October 2022
Download CSV 1.43 KB

Date identified with unsafe ACM cladding Tenure Remediation completed Works complete awaiting building control signoff Remediation started - cladding removed Remediation started Plans in place Responded with intent Remediation plan unclear / Awaiting further advice
Identified by 31 December 2019 Social sector residential 117 14 23 0 0 0 0
Identified by 31 December 2019 Private sector residential 134 20 16 11 6 0 0
Identified by 31 December 2019 Student accommodation 49 1 2 0 0 0 0
Identified by 31 December 2019 Hotels 21 2 0 3 0 1 0
Identified by 31 December 2019 Publicly-owned buildings 7 0 0 1 0 0 0
Identified by 31 December 2019 All tenures 328 37 41 15 6 1 0
Identified by 31 December 2020 Social sector residential 118 15 23 0 0 0 0
Identified by 31 December 2020 Private sector residential 144 22 22 15 8 1 0
Identified by 31 December 2020 Student accommodation 50 1 2 1 0 0 0
Identified by 31 December 2020 Hotels 21 3 0 4 0 1 0
Identified by 31 December 2020 Publicly-owned buildings 7 0 0 1 0 0 0
Identified by 31 December 2020 All tenures 340 41 47 21 8 2 0
All buildings identified Social sector residential 119 15 25 1 0 0 0
All buildings identified Private sector residential 147 25 22 16 13 7 1
All buildings identified Student accommodation 50 1 2 2 1 0 0
All buildings identified Hotels 22 3 0 4 0 2 0
All buildings identified Publicly-owned buildings 7 0 0 1 0 0 0
All buildings identified All tenures 345 44 49 24 14 9 1