Energy infrastructure: applications under consideration
Updated 4 October 2022
Download CSV 991 Bytes
Application / Acceptance date | Company / Location | Type of project / Consent requested |
---|---|---|
05.01.2022 | INRG SOLAR (Little Crow) Ltd/Little Crow Solar Park, near Scunthorpe, Lincolnshire | Solar Park and Battery Storage, Planning Act 2008 |
01.10.2021 | Lostock Sustainable Energy Limited/Lostock Sustainable Energy Park, near Northwich, Cheshire | Energy from Waste Generating Station, Section 36C Variation, Electricity Act 1989 |
24.06.2021 | RWE Generation UK plc/Little Barford Power Station, Little Barford, St Neots, Cambridgeshire | Gas-fired Generating Station, Section 36C Variation, Electricity Act 1989 |
24.06.2021 | RWE Generation UK plc/Staythorpe Power Station, between Southwell and Newark-on-Trent, Nottinghamshire | Gas-fired Generating Station, Section 36C Variation, Electricity Act 1989 |
14.10.2020 | National Grid Electricity Transmission/London Power Tunnels 2 Circuit 3 Hurst to Crayford | Compulsory Purchase Order, Electricity Act 1989 and Acquisition of Land Act 1981 |