Table 7: ACM remediation progress by date identified with unsafe ACM cladding and tenure, 30 June 2022
Updated 14 July 2022
Download CSV 1.44 KB
Date identified with unsafe ACM cladding | Tenure | Remediation completed | Works complete awaiting building control signoff | Remediation started - cladding removed | Remediation started | Plans in place | Responded with intent | Remediation plan unclear / Awaiting further advice |
---|---|---|---|---|---|---|---|---|
Identified by 31 December 2019 | Social sector residential | 107 | 23 | 24 | 0 | 0 | 0 | 0 |
Identified by 31 December 2019 | Private sector residential | 126 | 26 | 16 | 11 | 5 | 3 | 0 |
Identified by 31 December 2019 | Student accommodation | 48 | 2 | 2 | 0 | 0 | 0 | 0 |
Identified by 31 December 2019 | Hotels | 20 | 1 | 1 | 3 | 1 | 1 | 0 |
Identified by 31 December 2019 | Publicly-owned buildings | 7 | 0 | 0 | 1 | 0 | 0 | 0 |
Identified by 31 December 2019 | All tenures | 308 | 52 | 43 | 15 | 6 | 4 | 0 |
Identified by 31 December 2020 | Social sector residential | 107 | 25 | 24 | 0 | 0 | 0 | 0 |
Identified by 31 December 2020 | Private sector residential | 135 | 29 | 21 | 16 | 7 | 4 | 0 |
Identified by 31 December 2020 | Student accommodation | 49 | 2 | 2 | 1 | 0 | 0 | 0 |
Identified by 31 December 2020 | Hotels | 20 | 2 | 1 | 4 | 1 | 1 | 0 |
Identified by 31 December 2020 | Publicly-owned buildings | 7 | 0 | 0 | 1 | 0 | 0 | 0 |
Identified by 31 December 2020 | All tenures | 318 | 58 | 48 | 22 | 8 | 5 | 0 |
All buildings identified | Social sector residential | 107 | 26 | 26 | 1 | 0 | 0 | 0 |
All buildings identified | Private sector residential | 136 | 30 | 23 | 19 | 9 | 12 | 2 |
All buildings identified | Student accommodation | 49 | 2 | 2 | 2 | 1 | 0 | 0 |
All buildings identified | Hotels | 21 | 2 | 1 | 4 | 1 | 2 | 0 |
All buildings identified | Publicly-owned buildings | 7 | 0 | 0 | 1 | 0 | 0 | 0 |
All buildings identified | All tenures | 320 | 60 | 52 | 27 | 11 | 14 | 2 |